Riverbank Stabilisation and Scour Protection, River Laden

Client

Balfour Beatty

Duration

10 days

Location

River Laden, Bristol

Share

Erosion and scour were affecting the riverbanks around a bridge, with degradation visible around the bridge abutments and surrounding embankments. High Water was brought in to develop a practical stabilisation solution that would protect the banks while working sensitively within the existing watercourse environment.

The works covered approximately 36 linear metres of riverbank, extending around 6 metres upstream and downstream of the bridge on both banks. The existing erosion was causing continued loss of bank material, creating a need for a solution that could improve stability while limiting disruption to the surrounding environment.